OLMeRO Reference Projects


ARGE Prime Tower

To leave room for design and creativity, Mike Guyer believes that there's no getting around thinking carefully about how to classify the documents and structure the project and the associated information at the start of the work.

Name
Prime Tower
City
Zurich
Architect
Gigon/Guyer Architekten
Building owner
Swiss Prime Site AG
Construction period
2008-2011
Olmero in use
Repro service, Defect management, Tender platform, Project platform
Weiterlesen

Europaallee

In the middle of Zurich, a new district is being created. The variety of uses makes Europaallee and its surroundings an urban space that is animated at any time of the day by the resident population, service providers, gastronomy and pedestrians.

Name
Europaallee
City
Zurich
General contractor / total contractor
Implenia Generalunternehmung AG
Architect
Max Dudler Architekten AG, Zurich
Building owner
Lot 1: Switzerland. Bundesbahnen SBB
Lot 2: (Special construction): Building Department of the Canton of Zurich
Construction period
2009 - 2012
Olmero in use
Project platform, Tender platform
Weiterlesen

Commercial building at Schiffbauplatz

The new commercial building at Schiffbauplatz is being built in Zurich West. The new building comprises five to six floors of office and commercial space. The realization is expected to last until autumn 2017. Picture: Allreal

Name
Schiffbauplatz - Allreal
City
Zurich
General contractor / total contractor
Allreal Generalunternehmung AG, Zurich
Architect
Baukontor AG, Zurich
Building owner
Allreal West AG, Zurich
Construction period
2015-2017
Olmero in use
Tender platform
Weiterlesen

Entlisberg II + III replacement buildings

ABZ replaces the settlements Entlisberg II and III built in 1929/31 with modern new buildings (new Entlisberg 2). On the basis of the Entlisberg master plan, an architectural competition (study contract) was carried out, which was successfully concluded in summer 2013. The execution planning is currently being processed with the total contractor HRS Real Estate AG. Construction began in autumn 2015.

Name
Entlisberg II + III replacement buildings
City
Zurich
General contractor / total contractor
HRS Real Estate AG, Zurich
Construction period
2014-2016
Olmero in use
General
Weiterlesen

SunshineScenery

Urbanity and nature, the superstructure itself lives from these counterpoints. A garden-like complex extends between the buildings with urban architecture. All its beauty and wildness unfolds in the changing seasons.

Name
SunshineScenery
City
Uitikon
General contractor / total contractor
HRS Real Estate AG, Zurich
Construction period
2013 - 2015
Olmero in use
Defect management
Weiterlesen